Kalstø Operation

Equinor

untitled (20 of 61)
    • Method Air diving
    • Installation Kalstø

Monday, 04 April, was the start date for the Kalstø project 2019. First three days are set for familiarization at SubseaPartners base, both theoretical and practical project review to ensure efficiency and focus on HSE. Thursday 07th we set course for the operational area. The SOW for this year’s operation, was that all four vertical bearing affiliated Foundation 3 was replaced during this year’s operation.

Because of insufficient weather criteria within specified timeframes, Statoil decided to postpone part of the work to a phase-2 . Phase-2 startet August 22nd and ended September 14th. All performed activities related to this year’s scope was completed without any serious incidents.