Client: Equinor
Location: Gullfaks C Platform
Period: Feb – March 2025
Task: Mechanical Repair to Seawater Valve
Real Results:
Remedial work on seawater discharge valve controls
Challenge:
Control rods on seawater discharge valves were reported broken in the service shaft of the Gullfaks platform
Solution:
A portable dive spread was mobilised to the Gullfaks platform. Platform riggers installed a work platform inside the platform leg. After confined space recovery exercises, divers working alongside a rope access team changed out two of the spring supports